Key takeaways
- On 16 November 2026 the Minister of Water and Sanitation announced a 7% cut in domestic and industrial water allocations and a 15% cut in irrigation allocations across the Western Cape.
- Under section 22(1) of the National Water Act, water may be used only under Schedule 1, an existing lawful use, a general authorisation or a water use licence. General authorisations are narrow, and mining-related uses generally need a licence.
- Using water without a lawful basis is a criminal offence, and unregistered or unlicensed uses create risk in transactions, financing and enforcement.
On 16 November 2026, the Minister of Water and Sanitation, Pemmy Majodina, announced a 7% reduction in domestic and industrial water allocations and a 15% reduction in irrigation allocations across the Western Cape. The cuts follow the Department of Water and Sanitation’s (DWS) annual operating analysis of the Western Cape Water Supply System and are intended to guard against shortages linked to lower dam levels and a forecast strong El Niño.
Allocation cuts of this kind are a reminder that water is a regulated and increasingly contested resource. When supply tightens, the first question a regulator, a financier or a purchaser will ask of any business is whether its water use is lawful at all. The answer depends on a question that many projects never ask clearly at the outset: does this use require a water use licence, or is it covered by a general authorisation or another lawful basis?
The Starting Point: Section 21
The National Water Act 36 of 1998 (NWA) regulates eleven categories of water use, listed in section 21. They are –
- taking water from a water resource;
- storing water;
- impeding or diverting the flow of water in a watercourse;
- engaging in a stream flow reduction activity;
- engaging in a controlled activity, which includes irrigating land with waste or water containing waste;
- discharging waste or water containing waste into a water resource through a pipe, canal, sewer, sea outfall or other conduit;
- disposing of waste in a manner which may detrimentally impact on a water resource;
- disposing in any manner of water which contains waste from, or which has been heated in, any industrial or power generation process;
- altering the bed, banks, course or characteristics of a watercourse;
- removing, discharging or disposing of water found underground if it is necessary for the efficient continuation of an activity or for the safety of people; and
- using water for recreational purposes.
The definitions are wide. A single mining, industrial or infrastructure project will often involve several of them at once: abstraction from boreholes, storage in dams, road and pipeline crossings of watercourses, dewatering of workings and the management of process water and residue.
Four Routes To Lawful Water Use
Under section 22(1) of the NWA, a person may use water only if the use is permissible under one of the following routes –
- Schedule 1 – reasonable domestic use, small-scale non-commercial gardening, the watering of animals and similar low-impact uses;
- Existing lawful use – a use that was lawfully exercised during the two years before the NWA took effect on 1 October 1998, and which may continue, subject to verification and to any limits the responsible authority imposes;
- General authorisation – a use that falls within the scope and conditions of a general authorisation published under section 39; or
- Licence – a use authorised by a water use licence issued under sections 40 and 41.
The responsible authority may also dispense with the requirement for a licence in limited circumstances. In practice, however, the choice for most commercial projects is between a general authorisation and a licence.
General Authorisations: Useful, But Narrow
A general authorisation permits a defined category of use, within stated limits and subject to conditions, without the need for an individual licence. Many require the use to be registered, and the conditions must be met throughout. A use that falls outside any one of the limits, for example in volume, location or risk, is not authorised at all.
The general authorisation for section 21(c) and (i) water uses, published on 08 December 2023 (GN 4167 of 2023), illustrates the point. It covers a range of lower-risk activities in and near watercourses, such as certain linear infrastructure, maintenance work and small-scale projects, and it places considerable weight on the outcome of the prescribed risk assessment. It does not extend to activities with a medium or high risk rating, and it expressly excludes, among other things, water uses associated with mining and related infrastructure and with hazardous materials. Those uses require a licence.
When A Licence Is Required
A water use licence is required where no other route applies. Mines, in particular, will almost always need one: in addition to their mining right and environmental authorisation, most mining operations involve abstraction, storage, dewatering and the disposal of water containing waste, and are subject to the regulations on the use of water for mining and related activities (GN 704 of 1999).
The Water Use Licence Application and Appeals Regulations, 2017 require an application to be finalised within 300 days of submission. The DWS has committed to a shorter 90-day target and has published draft regulations to reduce the period, but applicants should still plan on the assumption that a complete and well-prepared application is the single biggest factor in timing. Licence decisions, including the conditions attached to a licence, may be appealed to the Water Tribunal under section 148 of the NWA, as the Tribunal’s decision in Canyon Resources earlier this year illustrates.
Registration Still Matters
Even a lawful use can create exposure if it is not properly registered. In April 2026, the Minister gave unregistered users of section 21(a) and 21(d) water uses 90 days to register, with a deadline of 23 July 2026. Changes of ownership, restructurings, name changes and unregistered commercial boreholes were all identified as common gaps, and each is relevant in transactions and due diligence.
A Practical Decision Path
For any new project, expansion or acquisition, the following sequence is a useful starting point –
- Identify every water use – map each activity against the eleven categories in section 21, including temporary construction-phase uses;
- Check Schedule 1 and existing lawful use – confirm whether any use is covered by Schedule 1, or by an existing lawful use that has been or can be verified;
- Test each remaining use against the general authorisations – check scope, thresholds, exclusions and risk rating, and confirm that every condition can be met for the life of the activity;
- Apply for a licence for everything else – ideally as a single integrated application, aligned with the environmental authorisation and, for mines, the mining right; and
- Register and keep records current – register uses where required and update registrations after any change of ownership, name or operation.
The Consequences Of Getting It Wrong
Using water without a lawful basis is an offence under the NWA, and a conviction may carry a fine, imprisonment of up to five years for a first offence, or both. Unlawful use can also lead to directives requiring the use to stop and the resource to be rehabilitated, delays in related authorisations, and difficulties with financiers and purchasers, who will expect a clear record of lawful water use. In a period of allocation cuts and closer regulatory scrutiny, those risks are increasing.
How Bishop Fraser Attorneys Can Assist
Water use authorisation sits between environmental, mining and land use law, and getting the route right at the outset saves considerable time and cost later.
Bishop Fraser Attorneys advises clients on identifying and authorising water uses under the NWA, the scope of general authorisations, water use licence applications and amendments, registration and compliance, appeals to the Water Tribunal, and water-related due diligence in mining, property and corporate transactions. Early legal engagement, before a project is designed around an assumption about its water uses, is almost always the more effective and less costly course.
Frequently asked questions
Do all water uses need a water use licence?
No. Under section 22(1) of the National Water Act, a water use may be permissible under Schedule 1, as an existing lawful use, under a general authorisation or under a licence. A licence is needed only where none of the other routes applies.
Can a mine rely on a general authorisation instead of a licence?
Generally not. The general authorisation for section 21(c) and (i) water uses excludes water uses associated with mining and related infrastructure, and most mines also abstract, store, dewater and dispose of water containing waste, which require a licence.
What happens if water is used without authorisation?
Unlawful water use is an offence under the National Water Act and may lead to a fine, imprisonment of up to five years for a first offence, or both. It can also lead to directives to stop the use and rehabilitate the resource, and complicate financing and transactions.